ITAC Assessment: OR0266
ITAC logo
ITAC Assessment: OR0266
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Aluminum Truck Parts
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 52,000
ft2
Annual Production 9,700,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $373,860 10,545,721
kWh
Electricity Demand $71,028 37,522
kW-mo/yr
Electricity Fees $19,386 -
Natural Gas $214,537 56,311
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $124,052 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,780

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 3.2135: Extend solution life with filtering or carbonate freezing $5,657 $2,800 $(-343.0)
(-9,672)
kWh
$(-58.0)
-
kW-mo/yr
- - $428
-
gal
$5,630
02 2.4224: Upgrade controls on compressors $16,123 $7,260 $13,716
385,698
kWh
$2,407
-
kW-mo/yr
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,329 $5,300 $2,753
77,374
kWh
$576
-
kW-mo/yr
- - - -
04 2.3212: Optimize plant power factor $3,043 $10,600 - - $3,043 - - -
05 2.1133: Adjust burners for efficient operation $70,500 $45,000 - - - $70,500
-
MMBtu
- -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $25,400 $179,000 $42,700
1,200,469
kWh
$10,500
-
kW-mo/yr
- $(-27,800.0)
-
MMBtu
- -
TOTAL RECOMMENDED $124,052 $249,960 $58,826
1,653,869
kWh
$13,425
-
kW-mo/yr
$3,043 $42,700
-
MMBtu
$428
-
gal
$5,630
TOTAL IMPLEMENTED $21,780 $10,060 $13,373
376,026
kWh
$2,349
-
kW-mo/yr
- - $428
-
gal
$5,630
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs