| Assessment Year | 2011 |
|---|---|
| Principal Product | Springs |
| NAICS | 332613: Spring Manufacturing |
| SIC | 3495: Wire Springs |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
80,000
ft2
|
| Annual Production | 6,000,000
lb
|
| Production Hrs. Annual | 4,810
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $137,208 | 1,527,919 |
kWh
|
$0.090 |
| Electricity Demand | $44,724 | 8,256 |
kW-mo/yr
|
$5.42 |
| Electricity Fees | $4,593 | - |
|
- |
| Natural Gas | $129,436 | 16,743 |
MMBtu
|
$7.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,510 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $48,430 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $17,840 | $28,410 | - |
$17,840
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,590 | $24,740 |
$11,700
130,000
kWh
|
$3,450
-
kW-mo/yr
|
$440 | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,240 | $13 |
$4,820
53,600
kWh
|
$1,420
-
kW-mo/yr
|
- | |
| 04 | 2.7145: Install skylights | $5,535 | - |
$5,535
61,500
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,810 | $500 |
$2,160
24,000
kWh
|
$650
-
kW-mo/yr
|
- | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,270 | $8,410 |
$980
10,900
kWh
|
$290
-
kW-mo/yr
|
- | |
| 07 | 2.4314: Use synthetic lubricant | $790 | - |
$610
6,760
kWh
|
$180
-
kW-mo/yr
|
- | |
| 08 | 2.7124: Make a practice of turning off lights when not needed | $530 | $325 |
$340
3,450
kWh
|
$190
-
kW-mo/yr
|
- | |
| 09 | 2.7124: Make a practice of turning off lights when not needed | $490 | $200 |
$490
5,450
kWh
|
- | - | |
| 10 | 2.3212: Optimize plant power factor | $415 | $1,270 | - |
$415
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $51,510 | $63,868 |
$26,635
295,660
kWh
|
$24,435
-
kW-mo/yr
|
$440 | ||
| TOTAL IMPLEMENTED | $48,430 | $54,933 |
$24,215
269,100
kWh
|
$23,775
-
kW-mo/yr
|
$440 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs