Assessment Year | 1996 |
---|---|
Principal Product | Extruded Aluminum Parts |
NAICS |
n/a
|
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
170,000
ft2
|
Annual Production | 64,000,000
lb
|
Production Hrs. Annual | 7,904
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $260,752 | 8,080,891 |
kWh
|
$0.032 |
Electricity Demand | $41,567 | 16,761 |
kW-mo/yr
|
$2.48 |
Electricity Fees | $17,533 | - |
|
- |
Natural Gas | $91,514 | 58,642 |
MMBtu
|
$1.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $260,922 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4111: Use closed cycle process to minimize waste water production | $35,059 | $1,690 |
$(-147.0)
(-4,396)
kWh
|
$(-22.0)
-
kW-mo/yr
|
- | - |
$25,566
-
Tgal
|
- | - |
$9,662
-
Tgal
|
|
02 | 3.5111: Filter and reuse hydraulic oil | $53,160 | $3,850 | - | - | - | - | - | - | $53,160 | - | |
03 | 3.1192: Reduce scrap production | $130,236 | $29,640 | - | - | - | - | - |
$133,200
-
lb
|
$(-2,964.0) | - | |
04 | 2.1113: Reduce combustion air flow to optimum | $28,400 | $8,250 | - | - | - |
$28,400
-
MMBtu
|
- | - | - | - | |
05 | 2.3212: Optimize plant power factor | $3,101 | $6,600 | - | - | $3,101 | - | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $4,084 | $10,701 |
$3,408
104,045
kWh
|
$676
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.4224: Upgrade controls on compressors | $6,882 | $27,454 |
$6,120
186,694
kWh
|
$762
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $260,922 | $88,185 |
$9,381
286,343
kWh
|
$1,416
-
kW-mo/yr
|
$3,101 |
$28,400
-
MMBtu
|
$25,566
-
Tgal
|
$133,200
-
lb
|
$50,196 |
$9,662
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs