ITAC Assessment: OR0167
ITAC logo
ITAC Assessment: OR0167
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product PCC calcium carbonate
NAICS
n/a
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 8
Plant Area
n/a
Annual Production 30,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $250,316 8,438,160
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,527 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,170

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7124: Make a practice of turning off lights when not needed $328 - $328
13,189
kWh
02 2.4133: Use most efficient type of electric motors $611 $1,171 $611
21,102
kWh
03 2.3212: Optimize plant power factor $6,403 $6,000 $6,403
-
kWh
04 2.4221: Install compressor air intakes in coolest locations $1,559 $7,500 $1,559
54,513
kWh
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $626 $2,150 $626
21,981
kWh
TOTAL RECOMMENDED $9,527 $16,821 $9,527
110,785
kWh
TOTAL IMPLEMENTED $2,170 $8,671 $2,170
75,615
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs