ITAC Assessment: OR0142
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product GREEN LUMBER AND VENEER
NAICS
n/a
SIC 2436: Softwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 475
Plant Area
n/a
Annual Production 74
thousand feet
Production Hrs. Annual 6,100
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $804,301 19,191,384
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,262 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,166

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Administrative Changes Savings
01 2.6232: Install set-back timers $769 - $603
20,223
kWh
- $166
02 2.7111: Reduce illumination to minimum necessary levels $1,013 - $721
24,033
kWh
- $292
03 2.3212: Optimize plant power factor $17,683 $13,500 $17,683
-
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $33,362 $45,000 $33,362
634,818
kWh
- -
05 2.2136: Install / repair insulation on steam lines $4,432 $8,712 - $4,432
-
MMBtu
-
06 2.4133: Use most efficient type of electric motors $619 $1,452 $619
11,723
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,191 - $1,568
42,204
kWh
- $(-377.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $193 - $276
5,862
kWh
- $(-83.0)
TOTAL RECOMMENDED $59,262 $68,664 $54,832
738,863
kWh
$4,432
-
MMBtu
$(-2.0)
TOTAL IMPLEMENTED $3,166 - $3,168
92,322
kWh
- $(-2.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs