| Assessment Year | 1992 |
|---|---|
| Principal Product | GREEN LUMBER AND VENEER |
| NAICS |
n/a
|
| SIC | 2436: Softwood Veneer and Plywood |
| Sales Range | $10 M to 50M |
| # of Employees | 475 |
| Plant Area |
n/a
|
| Annual Production | 74
thousand feet
|
| Production Hrs. Annual | 6,100
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $804,301 | 19,191,384 |
kWh
|
$0.042 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,262 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,166 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $769 | - |
$603
20,223
kWh
|
- | $166 | |
| 02 | 2.7111: Reduce illumination to minimum necessary levels | $1,013 | - |
$721
24,033
kWh
|
- | $292 | |
| 03 | 2.3212: Optimize plant power factor | $17,683 | $13,500 |
$17,683
-
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $33,362 | $45,000 |
$33,362
634,818
kWh
|
- | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $4,432 | $8,712 | - |
$4,432
-
MMBtu
|
- | |
| 06 | 2.4133: Use most efficient type of electric motors | $619 | $1,452 |
$619
11,723
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,191 | - |
$1,568
42,204
kWh
|
- | $(-377.0) | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $193 | - |
$276
5,862
kWh
|
- | $(-83.0) | |
| TOTAL RECOMMENDED | $59,262 | $68,664 |
$54,832
738,863
kWh
|
$4,432
-
MMBtu
|
$(-2.0) | ||
| TOTAL IMPLEMENTED | $3,166 | - |
$3,168
92,322
kWh
|
- | $(-2.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs