ITAC Assessment: OR0139
ITAC logo
ITAC Assessment: OR0139
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PRESSURE TREATED LUMBER
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 23,000
thousand feet
Production Hrs. Annual 2,080
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $181,376 6,389,215
kWh
Natural Gas $12,261 2,261
MMBtu
Wood $246,372 201,790
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,058 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,703

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Administrative Changes Savings
01 2.6232: Install set-back timers $633 - $452
23,154
kWh
- $181
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $291 - $291
7,620
kWh
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $17,876 $1,000 - $17,876
-
MMBtu
-
04 2.4239: Eliminate or reduce compressed air usage $11,685 $10,000 $11,685
597,304
kWh
- -
05 2.4133: Use most efficient type of electric motors $218 $4,614 $218
7,034
kWh
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,355 $61,690 $10,355
529,308
kWh
- -
TOTAL RECOMMENDED $41,058 $77,304 $23,001
1,164,420
kWh
$17,876
-
MMBtu
$181
TOTAL IMPLEMENTED $30,703 $15,614 $12,646
635,112
kWh
$17,876
-
MMBtu
$181
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs