ITAC Assessment: OR0111
ITAC logo
ITAC Assessment: OR0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product WOOLEN TEXTILES
NAICS
n/a
SIC 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing)
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area
n/a
Annual Production 135,000,000
pieces
Production Hrs. Annual 3,920
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,414 408,851
kWh
Natural Gas $42,007 10,754
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,875 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,875

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2123: Insulate feedwater tank $879 $379 - $879
-
MMBtu
-
02 2.6232: Install set-back timers $232 - $171
5,275
kWh
- $61
03 2.1233: Analyze flue gas for proper air/fuel ratio $877 $500 - $877
-
MMBtu
-
04 2.6232: Install set-back timers $1,153 - $782
23,447
kWh
- $371
05 2.1213: Direct warmest air to combustion intake $240 $470 - $240
-
MMBtu
-
06 2.3212: Optimize plant power factor $638 $1,350 $638
-
kWh
- -
07 2.2136: Install / repair insulation on steam lines $272 $671 - $272
-
MMBtu
-
08 2.4133: Use most efficient type of electric motors $58 $240 $58
1,172
kWh
- -
09 2.5191: Modify dye beck $1,526 $6,422 - $1,526
-
MMBtu
-
TOTAL RECOMMENDED $5,875 $10,032 $1,649
29,894
kWh
$3,794
-
MMBtu
$432
TOTAL IMPLEMENTED $5,875 $10,032 $1,649
29,894
kWh
$3,794
-
MMBtu
$432
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs