ITAC Assessment: OR0074
ITAC logo
ITAC Assessment: OR0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product SOFTWARE MANUALS
NAICS
n/a
SIC 2731: Books: Publishing, or Publishing and Printing
Sales Range $1
M
to 5
M
# of Employees 62
Plant Area
n/a
Annual Production 3,000,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,110 827,081
kWh
Natural Gas $7,515 1,592
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,069 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $869

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $171 $223 $171
3,224
kWh
02 2.2621: Modify refrigeration system to operate at a lower pressure $1,200 $2,400 $1,200
21,981
kWh
03 2.3212: Optimize plant power factor $498 $1,125 $498
-
kWh
04 2.4221: Install compressor air intakes in coolest locations $200 $250 $200
3,517
kWh
TOTAL RECOMMENDED $2,069 $3,998 $2,069
28,722
kWh
TOTAL IMPLEMENTED $869 $1,598 $869
6,741
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs