| Assessment Year | 1989 |
|---|---|
| Principal Product | DEHYDRATED FOOD |
| NAICS |
n/a
|
| SIC | 2034: Dried and Dehydrated Fruits, Vegetables, and Soup Mixes |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 3,900,000
lb
|
| Production Hrs. Annual | 8,064
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $298,319 | 7,283,119 |
kWh
|
$0.041 |
| Natural Gas | $86,224 | 23,541 |
MMBtu
|
$3.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $42,830 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.4154: Eliminate leaks in water lines and valves | $13,228 | $2,500 | - |
$11,331
-
MMBtu
|
$1,897 | |
| 02 | 3.4154: Eliminate leaks in water lines and valves | $12,697 | $2,400 | - |
$7,184
-
MMBtu
|
$5,513 | |
| 03 | 2.2441: Preheat boiler makeup water with waste process heat | $3,909 | $1,090 | - |
$3,198
-
MMBtu
|
$711 | |
| 04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $8,766 | - |
$8,766
219,226
kWh
|
- | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $1,113 | $1,204 |
$1,113
27,257
kWh
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $232 | $250 |
$232
5,862
kWh
|
- | - | |
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,260 | $2,000 | - |
$1,260
-
MMBtu
|
- | |
| 08 | 2.3212: Optimize plant power factor | $1,625 | $3,450 |
$1,625
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $42,830 | $12,894 |
$11,736
252,345
kWh
|
$22,973
-
MMBtu
|
$8,121 | ||
| TOTAL IMPLEMENTED | $42,830 | $12,894 |
$11,736
252,345
kWh
|
$22,973
-
MMBtu
|
$8,121 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs