ITAC Assessment: OR0066
ITAC logo
ITAC Assessment: OR0066
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product HARDBOARD
NAICS
n/a
SIC 2493: Reconstituted Wood Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 76,658
thousand feet
Production Hrs. Annual 7,488
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $858,680 19,913,248
kWh
Other Energy $557,126 526,001
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,449 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,062

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Other Energy Savings Administrative Changes Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $2,525 $110 $2,061
48,066
kWh
- $464
02 2.4221: Install compressor air intakes in coolest locations $1,778 $600 $1,778
41,325
kWh
- -
03 2.4133: Use most efficient type of electric motors $2,545 $1,252 $2,545
58,910
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,387 $2,392 $1,498
34,877
kWh
- $889
05 2.2444: Use hot process fluids to preheat incoming process fluids $3,480 $4,912 - $3,480
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $26,103 $36,047 $25,539
593,787
kWh
- $564
07 2.2136: Install / repair insulation on steam lines $631 $983 - $631
-
MMBtu
-
TOTAL RECOMMENDED $39,449 $46,296 $33,421
776,965
kWh
$4,111
-
MMBtu
$1,917
TOTAL IMPLEMENTED $37,062 $43,904 $31,923
742,088
kWh
$4,111
-
MMBtu
$1,028
Yearly Savings* Imp'd Cost* Electricity Usage Savings Other Energy Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs