Assessment Year | 1989 |
---|---|
Principal Product | HARDBOARD |
NAICS |
n/a
|
SIC | 2493: Reconstituted Wood Products |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 76,658
thousand feet
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $858,680 | 19,913,248 |
kWh
|
$0.043 |
Other Energy | $557,126 | 526,001 |
MMBtu
|
$1.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,449 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,062 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Energy Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $2,525 | $110 |
$2,061
48,066
kWh
|
- | $464 | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,778 | $600 |
$1,778
41,325
kWh
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $2,545 | $1,252 |
$2,545
58,910
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,387 | $2,392 |
$1,498
34,877
kWh
|
- | $889 | |
05 | 2.2444: Use hot process fluids to preheat incoming process fluids | $3,480 | $4,912 | - |
$3,480
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,103 | $36,047 |
$25,539
593,787
kWh
|
- | $564 | |
07 | 2.2136: Install / repair insulation on steam lines | $631 | $983 | - |
$631
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $39,449 | $46,296 |
$33,421
776,965
kWh
|
$4,111
-
MMBtu
|
$1,917 | ||
TOTAL IMPLEMENTED | $37,062 | $43,904 |
$31,923
742,088
kWh
|
$4,111
-
MMBtu
|
$1,028 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Energy Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs