ITAC Assessment: OR0058
ITAC logo
ITAC Assessment: OR0058
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product TITANIUM CASTINGS
NAICS
n/a
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area
n/a
Annual Production 171,169
lb
Production Hrs. Annual 4,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $131,400 2,706,038
kWh
Natural Gas $32,445 6,470
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,188 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,446

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.6218: Turn off equipment when not in use $8,281 - $8,281
242,673
kWh
-
02 2.3191: Use demand controller or load shedder $2,976 $200 $2,976
-
kWh
-
03 2.3191: Use demand controller or load shedder $1,940 $200 $1,940
-
kWh
-
04 3.4156: Use flow control valves on equipment to optimize water use $1,914 $200 - $1,914
05 2.4221: Install compressor air intakes in coolest locations $519 $250 $519
10,551
kWh
-
06 2.4133: Use most efficient type of electric motors $283 $172 $283
5,862
kWh
-
07 2.2514: Cover open tanks $1,428 - $1,428
41,911
kWh
-
08 2.2444: Use hot process fluids to preheat incoming process fluids $847 $1,170 $847
17,292
kWh
-
TOTAL RECOMMENDED $18,188 $2,192 $16,274
318,289
kWh
$1,914
TOTAL IMPLEMENTED $15,446 $1,570 $13,532
301,876
kWh
$1,914
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs