ITAC Assessment: OR0052
ITAC logo
ITAC Assessment: OR0052
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product FROZEN SOUPS, CAKES
NAICS
n/a
SIC 2038: Frozen Specialties, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area
n/a
Annual Production 52,800,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $269,347 12,810,082
kWh
Natural Gas $237,429 56,308
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,595 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,809

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $880 - $880
41,911
kWh
- -
02 2.6232: Install set-back timers $2,541 - $1,721
82,063
kWh
- $820
03 2.2621: Modify refrigeration system to operate at a lower pressure $6,550 $2,400 $6,550
312,134
kWh
- -
04 2.2414: Use waste heat from hot flue gases to preheat $411 $320 - $411
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,363 $500 - $1,363
-
MMBtu
-
06 2.2511: Insulate bare equipment $375 $385 - $375
-
MMBtu
-
07 2.2113: Repair or replace steam traps $8,216 $10,500 - $7,475
-
MMBtu
$741
08 2.4133: Use most efficient type of electric motors $259 $395 $259
12,309
kWh
- -
TOTAL RECOMMENDED $20,595 $14,500 $9,410
448,417
kWh
$9,624
-
MMBtu
$1,561
TOTAL IMPLEMENTED $19,809 $13,795 $9,410
448,417
kWh
$8,838
-
MMBtu
$1,561
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs