| Assessment Year | 1989 |
|---|---|
| Principal Product | FROZEN SOUPS, CAKES |
| NAICS |
n/a
|
| SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 52,800,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $269,347 | 12,810,082 |
kWh
|
$0.021 |
| Natural Gas | $237,429 | 56,308 |
MMBtu
|
$4.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,595 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,809 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $880 | - |
$880
41,911
kWh
|
- | - | |
| 02 | 2.6232: Install set-back timers | $2,541 | - |
$1,721
82,063
kWh
|
- | $820 | |
| 03 | 2.2621: Modify refrigeration system to operate at a lower pressure | $6,550 | $2,400 |
$6,550
312,134
kWh
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $411 | $320 | - |
$411
-
MMBtu
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,363 | $500 | - |
$1,363
-
MMBtu
|
- | |
| 06 | 2.2511: Insulate bare equipment | $375 | $385 | - |
$375
-
MMBtu
|
- | |
| 07 | 2.2113: Repair or replace steam traps | $8,216 | $10,500 | - |
$7,475
-
MMBtu
|
$741 | |
| 08 | 2.4133: Use most efficient type of electric motors | $259 | $395 |
$259
12,309
kWh
|
- | - | |
| TOTAL RECOMMENDED | $20,595 | $14,500 |
$9,410
448,417
kWh
|
$9,624
-
MMBtu
|
$1,561 | ||
| TOTAL IMPLEMENTED | $19,809 | $13,795 |
$9,410
448,417
kWh
|
$8,838
-
MMBtu
|
$1,561 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs