ITAC Assessment: OR0036
ITAC logo
ITAC Assessment: OR0036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product DAIRY PRODUCTS
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range n/a
# of Employees 160
Plant Area
n/a
Annual Production 11,300
Tgal
Production Hrs. Annual 4,992
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $226,701 4,733,880
kWh
Natural Gas $73,912 31,097
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,359 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,313

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $752 - $752
15,533
kWh
- -
02 2.2163: Use minimum steam operating pressure $523 - - $523
-
MMBtu
-
03 2.6232: Install set-back timers $855 - $617
12,896
kWh
- $238
04 2.1233: Analyze flue gas for proper air/fuel ratio $1,523 $300 - $1,523
-
MMBtu
-
05 2.2414: Use waste heat from hot flue gases to preheat $523 $200 - $523
-
MMBtu
-
06 2.4133: Use most efficient type of electric motors $129 $100 $129
2,638
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $54 $89 $42
879
kWh
- $12
TOTAL RECOMMENDED $4,359 $689 $1,540
31,946
kWh
$2,569
-
MMBtu
$250
TOTAL IMPLEMENTED $3,313 $489 $1,540
31,946
kWh
$1,523
-
MMBtu
$250
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs