Assessment Year | 1988 |
---|---|
Principal Product | LIFT TRUCKS ATTACHMENTS |
NAICS |
n/a
|
SIC | 3537: Industrial Trucks, Tractors, Trailers, and Stackers |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $228,425 | 4,199,004 |
kWh
|
$0.054 |
Natural Gas | $24,987 | 5,627 |
MMBtu
|
$4.44 |
Fuel Oil #6 | $4,057 | 1,520 |
MMBtu
|
$2.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,503 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,362 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $909 | $304 |
$909
16,706
kWh
|
- | - | |
02 | 2.7261: Install timers and/or thermostats | $1,762 | $1,250 |
$532
9,965
kWh
|
$1,230
-
MMBtu
|
- | |
03 | 2.2122: Install / repair insulation on condensate lines | $232 | $142 | - |
$232
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,969 | $6,119 |
$6,107
113,130
kWh
|
- | $(-138.0) | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $267 | $300 | - |
$267
-
MMBtu
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $99 | $146 |
$99
1,758
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $265 | $402 |
$451
8,206
kWh
|
- | $(-186.0) | |
TOTAL RECOMMENDED | $9,503 | $8,663 |
$8,098
149,765
kWh
|
$1,729
-
MMBtu
|
$(-324.0) | ||
TOTAL IMPLEMENTED | $8,362 | $8,217 |
$7,189
133,059
kWh
|
$1,497
-
MMBtu
|
$(-324.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs