ITAC Assessment: OR0021
ITAC logo
ITAC Assessment: OR0021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product POWER CONVERSION PROD.
NAICS
n/a
SIC 3612: Power, Distribution, and Specialty Transformers
Sales Range $10
M
to 50
M
# of Employees 850
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 0
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $314,855 5,922,626
kWh
Natural Gas $8,111 1,404
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,394 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,713

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $2,713 $200 $2,713
51,290
kWh
- -
02 2.7261: Install timers and/or thermostats $10,457 $5,000 $7,057
133,060
kWh
$3,400
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $572 $502 $548
10,258
kWh
- $24
04 2.7142: Utilize higher efficiency lamps and/or ballasts $22,545 $37,827 $18,949
357,562
kWh
- $3,596
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,107 $2,023 $1,170
21,981
kWh
- $(-63.0)
TOTAL RECOMMENDED $37,394 $45,552 $30,437
574,151
kWh
$3,400
-
MMBtu
$3,557
TOTAL IMPLEMENTED $2,713 $200 $2,713
51,290
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs