Assessment Year | 1987 |
---|---|
Principal Product | METAL CANS |
NAICS |
n/a
|
SIC | 3411: Metal Cans |
Sales Range | $10 M to 50M |
# of Employees | 57 |
Plant Area |
n/a
|
Annual Production | 146,600
pieces
|
Production Hrs. Annual | 4,950
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $56,690 | 1,668,523 |
kWh
|
$0.034 |
Natural Gas | $32,167 | 6,543 |
MMBtu
|
$4.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,081 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,959 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $4,816 | $20 | - |
$4,816
-
MMBtu
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $345 | - |
$345
10,258
kWh
|
- | - | |
03 | 2.7314: Reduce ventilation air | $4,062 | $11 |
$890
26,084
kWh
|
$3,172
-
MMBtu
|
- | |
04 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $3,646 | $1,700 |
$3,646
107,268
kWh
|
- | - | |
05 | 2.2511: Insulate bare equipment | $677 | $168 |
$677
39,566
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $7,065 | $5,550 | - |
$7,065
-
MMBtu
|
- | |
07 | 2.7492: Use proper thickness of insulation on building envelope | $8,339 | $6,586 | - |
$8,339
-
MMBtu
|
- | |
08 | 2.7492: Use proper thickness of insulation on building envelope | $4,413 | $3,346 | - |
$4,413
-
MMBtu
|
- | |
09 | 2.3212: Optimize plant power factor | $2,736 | $2,420 |
$2,736
-
kWh
|
- | - | |
10 | 2.7446: Utilize sensors controlling roof and wall openings | $49 | $80 |
$49
1,465
kWh
|
- | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,933 | $8,957 |
$1,580
46,600
kWh
|
- | $2,353 | |
TOTAL RECOMMENDED | $40,081 | $28,838 |
$9,923
231,241
kWh
|
$27,805
-
MMBtu
|
$2,353 | ||
TOTAL IMPLEMENTED | $11,959 | $2,451 |
$3,971
36,342
kWh
|
$7,988
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs