Assessment Year | 1998 |
---|---|
Principal Product | rubber hoses and ducts |
NAICS |
n/a
|
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
78,400
ft2
|
Annual Production | 504,995
lb
|
Production Hrs. Annual | 5,300
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $82,223 | 1,576,202 |
kWh
|
$0.052 |
Electricity Demand | $10,447 | 6,876 |
kW-mo/yr
|
$1.52 |
Natural Gas | $40,635 | 8,622 |
MMBtu
|
$4.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,160 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,160 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $12,990 | $46,170 |
$18,100
433,470
kWh
|
$1,860
-
kW-mo/yr
|
$(-6,970.0)
-
MMBtu
|
- | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $3,940 | $8,640 | - | - |
$3,940
-
MMBtu
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,850 | $7,290 |
$2,990
57,444
kWh
|
$210
-
kW-mo/yr
|
- | - | $(-350.0) | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,770 | $600 |
$2,600
49,824
kWh
|
$170
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,760 | $1,000 | - | - |
$1,220
-
MMBtu
|
- | $540 | - | |
06 | 2.4133: Use most efficient type of electric motors | $1,350 | $2,900 |
$1,270
24,326
kWh
|
$80
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $620 | $720 |
$210
4,103
kWh
|
$10
-
kW-mo/yr
|
- | - | $400 | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $570 | $250 |
$540
10,551
kWh
|
$30
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2437: Recover waste heat from equipment | $570 | $320 | - | - |
$570
-
MMBtu
|
- | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $520 | $250 |
$490
9,379
kWh
|
$30
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4314: Use synthetic lubricant | $430 | $610 |
$370
7,034
kWh
|
$20
-
kW-mo/yr
|
- | - | - | $40 | |
12 | 2.2511: Insulate bare equipment | $290 | $440 | - | - |
$290
-
MMBtu
|
- | - | - | |
13 | 2.2136: Install / repair insulation on steam lines | $240 | $390 | - | - |
$240
-
MMBtu
|
- | - | - | |
14 | 3.8122: Use tight-fitting lids on material containers to reduce voc emissions | $4,260 | $420 | - | - | - |
$4,260
-
gal
|
- | - | |
TOTAL RECOMMENDED | $33,160 | $70,000 |
$26,570
596,131
kWh
|
$2,410
-
kW-mo/yr
|
$(-710.0)
-
MMBtu
|
$4,260
-
gal
|
$590 | $40 | ||
TOTAL IMPLEMENTED | $10,160 | $13,150 |
$7,610
146,248
kWh
|
$500
-
kW-mo/yr
|
$1,460
-
MMBtu
|
- | $590 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs