ITAC Assessment: MA0781
ITAC logo
ITAC Assessment: MA0781
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Aerospace Components
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 50,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 8,568
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,961 1,385,280
kWh
Electricity Demand $73,371 5,593
kW-mo/yr
Electricity Fees $5,011 -
Natural Gas $28,061 1,524
MMBtu
TOTAL YEARLY COSTS $241,404
RECOMMENDED SAVINGS* $53,445 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,019

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.9113: Use solar heat for heat $33,144 $405,711 $33,144
341,692
kWh
- -
02 2.3212: Optimize plant power factor $7,386 $6,000 - $7,386
-
kW-mo/yr
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $10,896 $61,500 $13,139
135,462
kWh
$8,186
-
kW-mo/yr
$(-10,429.0)
-
MMBtu
04 2.7241: Install outside air damper / economizer on hvac unit $1,734 $2,724 $1,734
17,873
kWh
- -
05 2.2136: Install / repair insulation on steam lines $285 $215 $285
2,930
kWh
- -
TOTAL RECOMMENDED $53,445 $476,150 $48,302
497,957
kWh
$15,572
-
kW-mo/yr
$(-10,429.0)
-
MMBtu
TOTAL IMPLEMENTED $2,019 $2,939 $2,019
20,803
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs