| Assessment Year | 2025 |
|---|---|
| Principal Product | Titanium components for aerospace systems |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $50 M to 100M |
| # of Employees | 207 |
| Plant Area |
180,600
ft2
|
| Annual Production | 1,148,000
lb
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $577,047 | 14,426,178 |
kWh
|
$0.040 | |
| Electricity Demand | $652,074 | 28,650 |
kW-mo/yr
|
$22.76 | |
| Electricity Fees | $97,357 | - |
|
- | |
| Natural Gas | $77,547 | 20,142 |
MMBtu
|
$3.85 | |
| Waste Disposal Costs | |||||
| Water Usage | $154,982 | 18,485 |
Tgal
|
$8.38 | |
| Water Disposal | $141,777 | 18,485 |
Tgal
|
$7.67 | |
| TOTAL YEARLY COSTS | $1,700,784 | ||||
| RECOMMENDED SAVINGS* | $63,420 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $1,449 | - |
$1,449
36,218
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,811 | $2,884 |
$9,811
245,280
kWh
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,561 | $1,950 |
$3,561
89,046
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $1,934 | $20 | - | - |
$1,934
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $41,839 | $132,837 |
$26,999
674,973
kWh
|
$14,840
-
kW-mo/yr
|
- | |
| 06 | 2.2511: Insulate bare equipment | $488 | $653 |
$488
12,212
kWh
|
- | - | |
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $4,338 | $893 |
$4,338
108,449
kWh
|
- | - | |
| TOTAL RECOMMENDED | $63,420 | $139,237 |
$46,646
1,166,178
kWh
|
$14,840
-
kW-mo/yr
|
$1,934
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs