Assessment Year | 2024 |
---|---|
Principal Product | Fabricated metal products |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 388 |
Plant Area |
813,080
ft2
|
Annual Production | 5,100,000
lb
|
Production Hrs. Annual | 2,808
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $274,369 | 6,859,202 |
kWh
|
$0.040 | |
Electricity Demand | $389,698 | 18,356 |
kW-mo/yr
|
$21.23 | |
Electricity Fees | $20,841 | - |
|
- | |
Natural Gas | $120,458 | 19,101 |
MMBtu
|
$6.31 | |
Waste Disposal Costs | |||||
Water Usage | $35,373 | 2,947 |
Tgal
|
$12.00 | |
Water Disposal | $29,211 | 2,947 |
Tgal
|
$9.91 | |
TOTAL YEARLY COSTS | $869,950 | ||||
RECOMMENDED SAVINGS* | $248,272 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $62,690 | $117,898 |
$19,529
488,232
kWh
|
$43,161
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,625 | $8,880 |
$4,625
115,632
kWh
|
- | |
03 | 2.9114: Use solar heat to make electricty | $28,751 | $511,000 |
$28,751
718,782
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,780 | $520 |
$1,780
44,500
kWh
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $405 | $403 |
$235
5,869
kWh
|
$170
-
kW-mo/yr
|
|
06 | 2.7241: Install outside air damper / economizer on hvac unit | $25,553 | $5,538 |
$25,553
638,820
kWh
|
- | |
07 | 2.2622: Replace existing chiller with high efficiency model | $124,468 | $710,360 |
$28,275
706,867
kWh
|
$96,193
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $248,272 | $1,354,599 |
$108,748
2,718,702
kWh
|
$139,524
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs