ITAC Assessment: OK1124
ITAC logo
ITAC Assessment: OK1124
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Fabricated metal products
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 388
Plant Area 813,080
ft2
Annual Production 5,100,000
lb
Production Hrs. Annual 2,808
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,369 6,859,202
kWh
Electricity Demand $389,698 18,356
kW-mo/yr
Electricity Fees $20,841 -
Natural Gas $120,458 19,101
MMBtu
Waste Disposal Costs
Water Usage $35,373 2,947
Tgal
Water Disposal $29,211 2,947
Tgal
TOTAL YEARLY COSTS $869,950
RECOMMENDED SAVINGS* $248,272 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $62,690 $117,898 $19,529
488,232
kWh
$43,161
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,625 $8,880 $4,625
115,632
kWh
-
03 2.9114: Use solar heat to make electricty $28,751 $511,000 $28,751
718,782
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,780 $520 $1,780
44,500
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $405 $403 $235
5,869
kWh
$170
-
kW-mo/yr
06 2.7241: Install outside air damper / economizer on hvac unit $25,553 $5,538 $25,553
638,820
kWh
-
07 2.2622: Replace existing chiller with high efficiency model $124,468 $710,360 $28,275
706,867
kWh
$96,193
-
kW-mo/yr
TOTAL RECOMMENDED $248,272 $1,354,599 $108,748
2,718,702
kWh
$139,524
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs