Assessment Year | 2024 |
---|---|
Principal Product | Medical Services |
NAICS | 622110: General Medical and Surgical Hospitals |
SIC | 8062: General Medical and Surgical Hospitals |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
70,000
ft2
|
Annual Production | 500
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $322,976 | 4,378,920 |
kWh
|
$0.074 | |
Electricity Demand | $67,675 | 9,337 |
kW-mo/yr
|
$7.25 | |
Natural Gas | $142,116 | 33,449 |
MMBtu
|
$4.25 | |
Waste Disposal Costs | |||||
Water Usage | $6,379 | 1,529 |
Tgal
|
$4.17 | |
Water Disposal | $6,379 | 1,529 |
Tgal
|
$4.17 | |
TOTAL YEARLY COSTS | $545,525 | ||||
RECOMMENDED SAVINGS* | $120,160 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $52,945 | $56,850 |
$46,652
630,429
kWh
|
$6,293
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $3,264 | $1,330 |
$3,264
44,103
kWh
|
- | - | |
03 | 2.3212: Optimize plant power factor | $5,873 | $7,892 | - |
$5,873
-
kW-mo/yr
|
- | |
04 | 2.9114: Use solar heat to make electricty | $30,588 | $280,800 |
$30,588
413,357
kWh
|
- | - | |
05 | 2.1212: Operate boilers on high fire setting | $8,594 | $22,000 | - | - |
$8,594
-
MMBtu
|
|
06 | 2.2414: Use waste heat from hot flue gases to preheat | $15,219 | $12,400 | - | - |
$15,219
-
MMBtu
|
|
07 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $2,681 | $1,861 | - | - |
$2,681
-
MMBtu
|
|
08 | 2.4156: Establish a preventative maintenance program | $996 | $160 |
$996
13,455
kWh
|
- | - | |
TOTAL RECOMMENDED | $120,160 | $383,293 |
$81,500
1,101,344
kWh
|
$12,166
-
kW-mo/yr
|
$26,494
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs