Assessment Year | 2024 |
---|---|
Principal Product | Aircraft Parts and Auxiliary Equipment |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 80 |
Plant Area |
51,512
ft2
|
Annual Production | 5,200
units
|
Production Hrs. Annual | 3,744
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $69,251 | 865,636 |
kWh
|
$0.080 | |
Electricity Demand | $35,838 | 3,934 |
kW-mo/yr
|
$9.11 | |
Natural Gas | $31,616 | 1,622 |
MMBtu
|
$19.49 | |
Waste Disposal Costs | |||||
Water Usage | $2,216 | 198 |
Tgal
|
$11.19 | |
Water Disposal | $607 | 24 |
Tgal
|
$25.29 | |
TOTAL YEARLY COSTS | $139,528 | ||||
RECOMMENDED SAVINGS* | $34,947 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,354 | $29,487 |
$7,977
99,710
kWh
|
$2,377
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,075 | $1,600 |
$1,075
13,432
kWh
|
- | |
03 | 2.9114: Use solar heat to make electricty | $18,323 | $172,200 |
$18,323
229,040
kWh
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $405 | $503 |
$350
4,380
kWh
|
$55
-
kW-mo/yr
|
|
05 | 2.4239: Eliminate or reduce compressed air usage | $420 | - |
$420
5,256
kWh
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,784 | $906 |
$3,784
47,304
kWh
|
- | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $586 | $430 |
$577
7,213
kWh
|
$9
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $34,947 | $205,126 |
$32,506
406,335
kWh
|
$2,441
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs