| Assessment Year | 1992 |
|---|---|
| Principal Product | Aluminum Pistons |
| NAICS |
n/a
|
| SIC | 3592: Carburetors, Pistons, Piston Rings, and Valves |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
200,000
ft2
|
| Annual Production | 12,870,000
pieces
|
| Production Hrs. Annual | 4,682
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $439,525 | 8,772,861 |
kWh
|
$0.050 |
| Natural Gas | $138,159 | 67,395 |
MMBtu
|
$2.05 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $325,656 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $325,656 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,200 | $1,000 |
$7,200
143,611
kWh
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,880 | $500 |
$2,880
57,444
kWh
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,820 | $310 |
$1,820
36,342
kWh
|
- | - | - | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $8,920 | $8,750 |
$8,920
177,902
kWh
|
- | - | - | |
| 05 | 2.2514: Cover open tanks | $13,870 | $4,000 | - |
$13,870
-
MMBtu
|
- | - | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $176,510 | $40,000 | - |
$11,770
-
MMBtu
|
- | $164,740 | |
| 07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $84,970 | $120,000 |
$120,040
2,396,542
kWh
|
$(-35,070.0)
-
MMBtu
|
- | - | |
| 08 | 2.2511: Insulate bare equipment | $1,500 | $700 |
$1,500
29,894
kWh
|
- | - | - | |
| 09 | 2.6121: Reduce hot water temperature to the minimum required | $5,880 | $7,700 |
$5,880
117,233
kWh
|
- | - | - | |
| 10 | 2.7224: Reduce space conditioning during non-working hours | $300 | $150 |
$230
8,792
kWh
|
$70
-
MMBtu
|
- | - | |
| 11 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $106 | $900 | - | - | $106 | - | |
| 12 | 2.4234: Cool compressor air intake with heat exchanger | $14,750 | $20,280 |
$14,750
294,549
kWh
|
- | - | - | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,130 | $2,870 |
$6,130
122,216
kWh
|
- | - | - | |
| 14 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $820 | $2,610 |
$820
16,413
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $325,656 | $209,770 |
$170,170
3,400,938
kWh
|
$(-9,360.0)
-
MMBtu
|
$106 | $164,740 | ||
| TOTAL IMPLEMENTED | $325,656 | $209,770 |
$170,170
3,400,938
kWh
|
$(-9,360.0)
-
MMBtu
|
$106 | $164,740 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs