Assessment Year | 2024 |
---|---|
Principal Product | Industrial valves |
NAICS | 332911: Industrial Valve Manufacturing |
SIC | 3491: Industrial Valves |
Sales Range | $10 M to 50M |
# of Employees | 81 |
Plant Area |
110,000
ft2
|
Annual Production | 9,360
units
|
Production Hrs. Annual | 2,808
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $102,280 | 775,332 |
kWh
|
$0.13 | |
Natural Gas | $29,160 | 3,280 |
MMBtu
|
$8.89 | |
Waste Disposal Costs | |||||
Water Usage | $1,378 | 335 |
Tgal
|
$4.11 | |
Water Disposal | $1,699 | 335 |
Tgal
|
$5.07 | |
TOTAL YEARLY COSTS | $134,517 | ||||
RECOMMENDED SAVINGS* | $58,323 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $12,199 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,422 | $50,026 |
$10,422
78,958
kWh
|
- | |
02 | 2.9114: Use solar heat to make electricty | $40,554 | $187,200 |
$40,554
307,227
kWh
|
- | |
03 | 2.7231: Use radiant heater for spot heating | $2,649 | $5,850 | - |
$2,649
-
MMBtu
|
|
04 | 2.7241: Install outside air damper / economizer on hvac unit | $2,650 | $8,580 |
$2,650
20,072
kWh
|
- | |
05 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,777 | $4,495 |
$1,777
13,460
kWh
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $122 | $602 |
$122
927
kWh
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $149 | - |
$149
1,131
kWh
|
- | |
TOTAL RECOMMENDED | $58,323 | $256,753 |
$55,674
421,775
kWh
|
$2,649
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,199 | $54,521 |
$12,199
92,418
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs