Assessment Year | 2023 |
---|---|
Principal Product | Metal finishing |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
100,000
ft2
|
Annual Production | 480,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $266,425 | 3,620,400 |
kWh
|
$0.074 | |
Electricity Demand | $70,254 | 13,190 |
kW-mo/yr
|
$5.33 | |
Natural Gas | $373,806 | 37,804 |
MMBtu
|
$9.89 | |
Waste Disposal Costs | |||||
Water Usage | $45,856 | 12,484 |
Tgal
|
$3.67 | |
Water Disposal | $2,256 | 645 |
Tgal
|
$3.50 | |
TOTAL YEARLY COSTS | $758,597 | ||||
RECOMMENDED SAVINGS* | $25,782 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $25,782 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,064 | $22,000 | - | - |
$5,064
-
MMBtu
|
|
02 | 2.7232: Replace existing hvac unit with high efficiency model | $2,905 | $14,300 |
$2,905
39,258
kWh
|
- | - | |
03 | 2.7211: Clean and maintain refrigerant condensers and towers | $4,600 | $2,921 |
$4,040
54,600
kWh
|
$560
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,067 | - |
$2,067
27,930
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,107 | $2,128 |
$10,107
136,581
kWh
|
- | - | |
06 | 2.7444: Close holes and openings in building such as broken windows | $1,039 | $2,100 | - | - |
$1,039
-
MMBtu
|
|
TOTAL RECOMMENDED | $25,782 | $43,449 |
$19,119
258,369
kWh
|
$560
-
kW-mo/yr
|
$6,103
-
MMBtu
|
||
TOTAL IMPLEMENTED | $25,782 | $43,449 |
$19,119
258,369
kWh
|
$560
-
kW-mo/yr
|
$6,103
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs