| Assessment Year | 2023 |
|---|---|
| Principal Product | Furniture for commercial & institutional applications |
| NAICS | 337127: Institutional Furniture Manufacturing |
| SIC | 2599: Furniture and Fixtures, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
100,000
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $57,711 | 918,080 |
kWh
|
$0.063 | |
| Electricity Demand | $34,716 | 5,710 |
kW-mo/yr
|
$6.08 | |
| Electricity Fees | $951 | - |
|
- | |
| Natural Gas | $43,306 | 7,769 |
MMBtu
|
$5.57 | |
| LPG | $7,181 | 162 |
MMBtu
|
$44.46 | |
| Waste Disposal Costs | |||||
| Water Usage | $4,070 | 814 |
Tgal
|
$5.00 | |
| Water Disposal | $5,181 | 803 |
Tgal
|
$6.45 | |
| TOTAL YEARLY COSTS | $153,116 | ||||
| RECOMMENDED SAVINGS* | $44,062 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $3,642 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,012 | $1,489 |
$3,012
47,803
kWh
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $630 | $330 |
$531
8,428
kWh
|
$99
-
kW-mo/yr
|
- | |
| 03 | 2.7231: Use radiant heater for spot heating | $8,472 | $13,560 | - | - |
$8,472
-
MMBtu
|
|
| 04 | 2.9114: Use solar heat to make electricty | $31,948 | $382,200 |
$31,522
500,344
kWh
|
$426
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $44,062 | $397,579 |
$35,065
556,575
kWh
|
$525
-
kW-mo/yr
|
$8,472
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,642 | $1,819 |
$3,543
56,231
kWh
|
$99
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs