Assessment Year | 2006 |
---|---|
Principal Product | Drugs of Abuse Test Kits |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2835: In Vitro and In Vivo Diagnostic Substances |
Sales Range | $50 M to 100M |
# of Employees | 270 |
Plant Area |
90,000
ft2
|
Annual Production | 45,000,000
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $210,970 | 2,208,699 |
kWh
|
$0.096 |
Electricity Demand | $90,154 | 6,546 |
kW-mo/yr
|
$13.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $69,006 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,759 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $9,667 | - |
$9,667
86,009
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $50,318 | $20,000 |
$10,884
96,818
kWh
|
$39,434
-
kW-mo/yr
|
- | |
03 | 2.2511: Insulate bare equipment | $1,729 | $937 | - | - |
$1,729
-
MMBtu
|
|
04 | 2.7135: Install occupancy sensors | $3,650 | $3,344 |
$1,990
16,990
kWh
|
$1,660
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,534 | $3,510 |
$821
7,301
kWh
|
$713
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,179 | $3,376 |
$980
8,711
kWh
|
$199
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $929 | $3,460 |
$497
4,418
kWh
|
$432
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $69,006 | $34,627 |
$24,839
220,247
kWh
|
$42,438
-
kW-mo/yr
|
$1,729
-
MMBtu
|
||
TOTAL IMPLEMENTED | $17,759 | $11,167 |
$13,458
119,011
kWh
|
$2,572
-
kW-mo/yr
|
$1,729
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs