| Assessment Year | 2006 |
|---|---|
| Principal Product | Drugs of Abuse Test Kits |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2835: In Vitro and In Vivo Diagnostic Substances |
| Sales Range | $50 M to 100M |
| # of Employees | 270 |
| Plant Area |
90,000
ft2
|
| Annual Production | 45,000,000
pieces
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $210,970 | 2,208,699 |
kWh
|
$0.096 |
| Electricity Demand | $90,154 | 6,546 |
kW-mo/yr
|
$13.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $69,006 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,759 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $9,667 | - |
$9,667
86,009
kWh
|
- | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $50,318 | $20,000 |
$10,884
96,818
kWh
|
$39,434
-
kW-mo/yr
|
- | |
| 03 | 2.2511: Insulate bare equipment | $1,729 | $937 | - | - |
$1,729
-
MMBtu
|
|
| 04 | 2.7135: Install occupancy sensors | $3,650 | $3,344 |
$1,990
16,990
kWh
|
$1,660
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,534 | $3,510 |
$821
7,301
kWh
|
$713
-
kW-mo/yr
|
- | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,179 | $3,376 |
$980
8,711
kWh
|
$199
-
kW-mo/yr
|
- | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $929 | $3,460 |
$497
4,418
kWh
|
$432
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $69,006 | $34,627 |
$24,839
220,247
kWh
|
$42,438
-
kW-mo/yr
|
$1,729
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,759 | $11,167 |
$13,458
119,011
kWh
|
$2,572
-
kW-mo/yr
|
$1,729
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs