| Assessment Year | 2020 |
|---|---|
| Principal Product | Potable water |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $100 M to 500M |
| # of Employees | 26 |
| Plant Area |
115,960
ft2
|
| Annual Production | 21,170,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $682,150 | 27,286,000 |
kWh
|
$0.025 | |
| Electricity Demand | $276,258 | 51,349 |
kW-mo/yr
|
$5.38 | |
| Electricity Fees | $3,360 | - |
|
- | |
| Natural Gas | $9,916 | 3,158 |
MMBtu
|
$3.14 | |
| Waste Disposal Costs | |||||
| Water Usage | $35,148 | 6,232 |
Tgal
|
$5.64 | |
| TOTAL YEARLY COSTS | $1,006,832 | ||||
| RECOMMENDED SAVINGS* | $25,997 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $563 | $1,944 |
$563
22,524
kWh
|
- | - | |
| 02 | 3.4153: Use counter current rinsing to reduce waste water | $24,443 | $2,171 | - | - |
$24,443
-
Tgal
|
|
| 03 | 2.7261: Install timers and/or thermostats | $991 | - |
$341
13,644
kWh
|
$650
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $25,997 | $4,115 |
$904
36,168
kWh
|
$650
-
MMBtu
|
$24,443
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs