ITAC Assessment: OK1038
ITAC logo
ITAC Assessment: OK1038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Potable water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $100
M
to 500
M
# of Employees 26
Plant Area 115,960
ft2
Annual Production 21,170,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $682,150 27,286,000
kWh
Electricity Demand $276,258 51,349
kW-mo/yr
Electricity Fees $3,360 -
Natural Gas $9,916 3,158
MMBtu
Waste Disposal Costs
Water Usage $35,148 6,232
Tgal
TOTAL YEARLY COSTS $1,006,832
RECOMMENDED SAVINGS* $25,997 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings
01 2.7135: Install occupancy sensors $563 $1,944 $563
22,524
kWh
- -
02 3.4153: Use counter current rinsing to reduce waste water $24,443 $2,171 - - $24,443
-
Tgal
03 2.7261: Install timers and/or thermostats $991 - $341
13,644
kWh
$650
-
MMBtu
-
TOTAL RECOMMENDED $25,997 $4,115 $904
36,168
kWh
$650
-
MMBtu
$24,443
-
Tgal
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs