ITAC Assessment: OK1036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Potable water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $100
M
to 500
M
# of Employees 28
Plant Area 80,166
ft2
Annual Production 21,900,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $804,018 28,714,933
kWh
Electricity Demand $308,521 57,346
kW-mo/yr
Electricity Fees $3,360 -
Natural Gas $22,407 7,519
MMBtu
Waste Disposal Costs
Water Usage $66,394 11,772
Tgal
TOTAL YEARLY COSTS $1,204,700
RECOMMENDED SAVINGS* $45,250 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $942

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings
01 2.7135: Install occupancy sensors $450 $1,163 $450
16,074
kWh
- -
02 3.4153: Use counter current rinsing to reduce waste water $43,157 $12,222 - - $43,157
-
Tgal
03 2.7231: Use radiant heater for spot heating $1,151 $3,500 - $1,151
-
MMBtu
-
04 2.7232: Replace existing hvac unit with high efficiency model $209 $1,390 $209
7,450
kWh
- -
05 2.7261: Install timers and/or thermostats $283 $312 - $283
-
MMBtu
-
TOTAL RECOMMENDED $45,250 $18,587 $659
23,524
kWh
$1,434
-
MMBtu
$43,157
-
Tgal
TOTAL IMPLEMENTED $942 $2,865 $659
23,524
kWh
$283
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs