| Assessment Year | 2020 |
|---|---|
| Principal Product | Gray and ductile iron castings |
| NAICS | 331511: Iron Foundries |
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $5 M to 10M |
| # of Employees | 45 |
| Plant Area |
65,000
ft2
|
| Annual Production | 3,960,000
lb
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $183,024 | 3,050,400 |
kWh
|
$0.060 | |
| Electricity Demand | $124,203 | 14,066 |
kW-mo/yr
|
$8.83 | |
| Electricity Fees | $216 | - |
|
- | |
| Natural Gas | $34,375 | 5,787 |
MMBtu
|
$5.94 | |
| Waste Disposal Costs | |||||
| Water Usage | $9,500 | 2,500 |
Tgal
|
$3.80 | |
| TOTAL YEARLY COSTS | $351,318 | ||||
| RECOMMENDED SAVINGS* | $15,664 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $13,265 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,433 | $2,100 |
$5,433
90,555
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,570 | $27,786 |
$4,836
80,595
kWh
|
$2,734
-
kW-mo/yr
|
- | |
| 03 | 2.7232: Replace existing hvac unit with high efficiency model | $262 | $700 |
$209
3,488
kWh
|
$53
-
kW-mo/yr
|
- | |
| 04 | 2.7261: Install timers and/or thermostats | $343 | - |
$147
2,450
kWh
|
- |
$196
-
MMBtu
|
|
| 05 | 2.3191: Use demand controller or load shedder | $2,056 | $671 | - |
$2,056
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $15,664 | $31,257 |
$10,625
177,088
kWh
|
$4,843
-
kW-mo/yr
|
$196
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,265 | $30,586 |
$10,478
174,638
kWh
|
$2,787
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs