| Assessment Year | 2020 |
|---|---|
| Principal Product | Aircraft parts |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
200,000
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $215,774 | 1,751,120 |
kWh
|
$0.12 | |
| Natural Gas | $27,203 | 3,790 |
MMBtu
|
$7.18 | |
| Waste Disposal Costs | |||||
| Water Usage | $20,100 | 5,500 |
Tgal
|
$3.65 | |
| TOTAL YEARLY COSTS | $263,077 | ||||
| RECOMMENDED SAVINGS* | $68,338 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $53,270 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $37,935 | $21,052 |
$37,935
307,912
kWh
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,015 | $8,099 |
$13,015
105,641
kWh
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,053 | $4,865 |
$2,053
16,661
kWh
|
|
| 04 | 2.4221: Install compressor air intakes in coolest locations | $6,011 | $1,186 |
$6,011
48,793
kWh
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,590 | $745 |
$5,590
45,377
kWh
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,734 | - |
$3,734
30,310
kWh
|
|
| TOTAL RECOMMENDED | $68,338 | $35,947 |
$68,338
554,694
kWh
|
||
| TOTAL IMPLEMENTED | $53,270 | $22,983 |
$53,270
432,392
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs