Assessment Year | 2020 |
---|---|
Principal Product | Electric motors, water system, fueling system |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $50 M to 100M |
# of Employees | 350 |
Plant Area |
332,000
ft2
|
Annual Production | 39,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $487,311 | 9,429,700 |
kWh
|
$0.052 | |
Electricity Demand | $158,344 | 52,096 |
kW-mo/yr
|
$3.04 | |
Electricity Fees | $7,729 | - |
|
- | |
Natural Gas | $101,361 | 16,936 |
MMBtu
|
$5.98 | |
LPG | $20,419 | 981 |
MMBtu
|
$20.81 | |
Waste Disposal Costs | |||||
Water Usage | $13,121 | 301 |
Tgal
|
$43.59 | |
TOTAL YEARLY COSTS | $788,285 | ||||
RECOMMENDED SAVINGS* | $51,648 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $49,321 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $34,672 | $127,500 | - | - |
$34,672
-
MMBtu
|
- | |
02 | 2.7261: Install timers and/or thermostats | $3,684 | $2,420 | - | - |
$3,684
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $5,805 | $65 |
$5,805
111,629
kWh
|
- | - | - | |
04 | 2.1113: Reduce combustion air flow to optimum | $3,427 | $1,500 | - | - |
$3,427
-
MMBtu
|
- | |
05 | 2.6211: Conserve energy by efficient use of vending machines | $1,779 | $2,207 |
$1,779
34,206
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,733 | $8,651 |
$1,368
26,312
kWh
|
$365
-
kW-mo/yr
|
- | - | |
07 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $548 | - | - | - | - |
$548
-
MMBtu
|
|
TOTAL RECOMMENDED | $51,648 | $142,343 |
$8,952
172,147
kWh
|
$365
-
kW-mo/yr
|
$41,783
-
MMBtu
|
$548
-
MMBtu
|
||
TOTAL IMPLEMENTED | $49,321 | $140,136 |
$7,173
137,941
kWh
|
$365
-
kW-mo/yr
|
$41,783
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs