ITAC Assessment: OK1009
ITAC logo
ITAC Assessment: OK1009
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Air Filters
NAICS 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 336
Plant Area 451,400
ft2
Annual Production 104,752
units
Production Hrs. Annual 4,992
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $184,269 4,244,240
kWh
Electricity Demand $92,022 8,596
kW-mo/yr
Electricity Fees $4,692 -
Natural Gas $20,423 4,228
MMBtu
Waste Disposal Costs
Water Usage $3,237 1,015
Tgal
TOTAL YEARLY COSTS $304,643
RECOMMENDED SAVINGS* $29,979 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,566

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7232: Replace existing hvac unit with high efficiency model $8,453 $37,361 $4,919
114,400
kWh
$3,534
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,469 $833 $2,469
57,412
kWh
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,224 - $2,224
51,724
kWh
- - -
04 2.3132: Recharge batteries on during off-peak demand periods $7,915 - - $7,915
-
kW-mo/yr
- -
05 2.3212: Optimize plant power factor $365 $1,365 - - $365 -
06 2.8123: Pay utility bills on time $371 - - - $371 -
07 2.7261: Install timers and/or thermostats $8,182 $1,430 - - - $8,182
-
MMBtu
TOTAL RECOMMENDED $29,979 $40,989 $9,612
223,536
kWh
$11,449
-
kW-mo/yr
$736 $8,182
-
MMBtu
TOTAL IMPLEMENTED $18,566 $2,263 $2,469
57,412
kWh
$7,915
-
kW-mo/yr
- $8,182
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs