| Assessment Year | 2018 |
|---|---|
| Principal Product | wood products |
| NAICS | 321219: Reconstituted Wood Product Manufacturing |
| SIC | 2493: Reconstituted Wood Products |
| Sales Range | $100 M to 500M |
| # of Employees | 90 |
| Plant Area |
600,000
ft2
|
| Annual Production | 19,687,500
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $3,849,410 | 75,644,740 |
kWh
|
$0.051 | |
| Electricity Demand | $375,068 | 117,563 |
kW-mo/yr
|
$3.19 | |
| Natural Gas | $718,178 | 236,492 |
MMBtu
|
$3.04 | |
| Waste Disposal Costs | |||||
| Water Usage | $142,382 | 593 |
Tgal
|
$240.10 | |
| TOTAL YEARLY COSTS | $5,085,038 | ||||
| RECOMMENDED SAVINGS* | $192,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $190,577 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,205 | $944 |
$1,205
23,630
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $184,161 | $201,131 |
$169,706
3,327,574
kWh
|
$14,455
-
kW-mo/yr
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,686 | $6,881 |
$1,553
30,441
kWh
|
$133
-
kW-mo/yr
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,730 | $13,456 |
$4,730
92,742
kWh
|
- | |
| 05 | 2.7232: Replace existing hvac unit with high efficiency model | $616 | $5,983 |
$480
9,395
kWh
|
$136
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $192,398 | $228,395 |
$177,674
3,483,782
kWh
|
$14,724
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $190,577 | $221,468 |
$175,989
3,450,757
kWh
|
$14,588
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs