ITAC Assessment: OK0985
ITAC logo
ITAC Assessment: OK0985
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Vehicle Bumpers
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 500
Plant Area 350,000
ft2
Annual Production 400,000
units
Production Hrs. Annual 6,864
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,415,030 40,429,440
kWh
Electricity Demand $48,934 6,314
kW-mo/yr
Natural Gas $385,279 76,308
MMBtu
TOTAL YEARLY COSTS $1,849,243
RECOMMENDED SAVINGS* $117,326 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,042

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6232: Install set-back timers $758 $592 $283
8,092
kWh
- $475
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $17,240 $19,498 $16,697
477,062
kWh
$543
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,769 $21,562 $4,622
132,064
kWh
$147
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,033 $7,422 $2,033
58,089
kWh
- -
05 2.6231: Utilize controls to operate equipment only when needed $12,555 $3,157 $12,555
358,718
kWh
- -
06 2.2511: Insulate bare equipment $79,971 $7,481 $79,971
2,284,887
kWh
- -
TOTAL RECOMMENDED $117,326 $59,712 $116,161
3,318,912
kWh
$690
-
kW-mo/yr
$475
-
MMBtu
TOTAL IMPLEMENTED $24,042 $48,482 $23,352
667,215
kWh
$690
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs