| Assessment Year | 2018 |
|---|---|
| Principal Product | Vehicle Bumpers |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 500 |
| Plant Area |
350,000
ft2
|
| Annual Production | 400,000
units
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,415,030 | 40,429,440 |
kWh
|
$0.035 |
| Electricity Demand | $48,934 | 6,314 |
kW-mo/yr
|
$7.75 |
| Natural Gas | $385,279 | 76,308 |
MMBtu
|
$5.05 |
| TOTAL YEARLY COSTS | $1,849,243 | |||
| RECOMMENDED SAVINGS* | $117,326 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,042 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $758 | $592 |
$283
8,092
kWh
|
- |
$475
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,240 | $19,498 |
$16,697
477,062
kWh
|
$543
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,769 | $21,562 |
$4,622
132,064
kWh
|
$147
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,033 | $7,422 |
$2,033
58,089
kWh
|
- | - | |
| 05 | 2.6231: Utilize controls to operate equipment only when needed | $12,555 | $3,157 |
$12,555
358,718
kWh
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $79,971 | $7,481 |
$79,971
2,284,887
kWh
|
- | - | |
| TOTAL RECOMMENDED | $117,326 | $59,712 |
$116,161
3,318,912
kWh
|
$690
-
kW-mo/yr
|
$475
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $24,042 | $48,482 |
$23,352
667,215
kWh
|
$690
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs