| Assessment Year | 2017 |
|---|---|
| Principal Product | Glass containers |
| NAICS | 327213: Glass Container Manufacturing |
| SIC | 3221: Glass Containers |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
520,000
ft2
|
| Annual Production | 730,000,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $2,485,950 | 71,371,200 |
kWh
|
$0.035 | |
| Electricity Demand | $594,657 | 108,337 |
kW-mo/yr
|
$5.49 | |
| Natural Gas | $2,717,617 | 879,684 |
MMBtu
|
$3.09 | |
| Waste Disposal Costs | |||||
| Water Usage | $85,089 | 19,972 |
Tgal
|
$4.26 | |
| TOTAL YEARLY COSTS | $5,883,313 | ||||
| RECOMMENDED SAVINGS* | $534,717 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $124,716 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $124,716 | $75,000 |
$102,657
2,933,069
kWh
|
$22,058
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,815 | - |
$6,433
183,796
kWh
|
$1,382
-
kW-mo/yr
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $16,309 | $4,937 |
$16,309
465,964
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,343 | $69,050 |
$17,568
501,948
kWh
|
$3,775
-
kW-mo/yr
|
- | |
| 05 | 2.2421: Install waste heat boiler to provide direct power | $353,111 | $2,500,000 |
$290,657
8,304,480
kWh
|
$62,454
-
kW-mo/yr
|
- | |
| 06 | 2.3212: Optimize plant power factor | $11,423 | $50,570 | - | - | $11,423 | |
| TOTAL RECOMMENDED | $534,717 | $2,699,557 |
$433,624
12,389,257
kWh
|
$89,670
-
kW-mo/yr
|
$11,423 | ||
| TOTAL IMPLEMENTED | $124,716 | $75,000 |
$102,657
2,933,069
kWh
|
$22,058
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs