ITAC Assessment: OK0981
ITAC logo
ITAC Assessment: OK0981
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Glass containers
NAICS 327213: Glass Container Manufacturing
SIC 3221: Glass Containers
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 520,000
ft2
Annual Production 730,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,485,950 71,371,200
kWh
Electricity Demand $594,657 108,337
kW-mo/yr
Natural Gas $2,717,617 879,684
MMBtu
Waste Disposal Costs
Water Usage $85,089 19,972
Tgal
TOTAL YEARLY COSTS $5,883,313
RECOMMENDED SAVINGS* $534,717 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $124,716

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.4224: Upgrade controls on compressors $124,716 $75,000 $102,657
2,933,069
kWh
$22,058
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $7,815 - $6,433
183,796
kWh
$1,382
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $16,309 $4,937 $16,309
465,964
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $21,343 $69,050 $17,568
501,948
kWh
$3,775
-
kW-mo/yr
-
05 2.2421: Install waste heat boiler to provide direct power $353,111 $2,500,000 $290,657
8,304,480
kWh
$62,454
-
kW-mo/yr
-
06 2.3212: Optimize plant power factor $11,423 $50,570 - - $11,423
TOTAL RECOMMENDED $534,717 $2,699,557 $433,624
12,389,257
kWh
$89,670
-
kW-mo/yr
$11,423
TOTAL IMPLEMENTED $124,716 $75,000 $102,657
2,933,069
kWh
$22,058
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs