Assessment Year | 2017 |
---|---|
Principal Product | Aerospace Composites |
NAICS | 336411: Aircraft Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 28 |
Plant Area |
58,000
ft2
|
Annual Production | 10,000,000
lb
|
Production Hrs. Annual | 4,015
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $139,936 | 1,220,480 |
kWh
|
$0.11 |
Electricity Demand | $13,660 | 1,952 |
kW-mo/yr
|
$7.00 |
Natural Gas | $46,958 | 7,619 |
MMBtu
|
$6.16 |
TOTAL YEARLY COSTS | $200,554 | |||
RECOMMENDED SAVINGS* | $32,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $2,612 | $910 | - | - | - |
$2,612
-
MMBtu
|
|
02 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $609 | $912 | - | - | - |
$609
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,920 | $14,920 |
$3,920
34,091
kWh
|
$1,000
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $871 | $1,272 |
$871
7,577
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,443 | $2,300 |
$1,443
10,096
kWh
|
- | - | - | |
06 | 2.3212: Optimize plant power factor | $16,088 | $1,209 | - | - | $16,088 | - | |
07 | 2.7211: Clean and maintain refrigerant condensers and towers | $67 | $208 |
$67
584
kWh
|
- | - | - | |
08 | 2.2514: Cover open tanks | $5,491 | $1,301 | - | - | - |
$5,491
-
MMBtu
|
|
TOTAL RECOMMENDED | $32,101 | $23,032 |
$6,301
52,348
kWh
|
$1,000
-
kW-mo/yr
|
$16,088 |
$8,712
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs