ITAC Assessment: OK0975
ITAC logo
ITAC Assessment: OK0975
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Aircraft manufacturing & assembly
NAICS 336411: Aircraft Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 210
Plant Area 172,515
ft2
Annual Production 710,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $317,872 6,852,113
kWh
Electricity Demand $302,611 15,723
kW-mo/yr
Electricity Fees $1,866 -
Natural Gas $14,836 2,823
MMBtu
TOTAL YEARLY COSTS $637,185
RECOMMENDED SAVINGS* $69,498 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $25,427 $24,531 - - $25,427 -
02 2.7232: Replace existing hvac unit with high efficiency model $19,832 $46,320 $9,110
198,037
kWh
$10,722
-
kW-mo/yr
- -
03 2.7241: Install outside air damper / economizer on hvac unit $9,584 $9,120 $9,584
208,352
kWh
- - -
04 2.7211: Clean and maintain refrigerant condensers and towers $2,312 $1,015 $1,061
23,061
kWh
$1,251
-
kW-mo/yr
- -
05 2.7224: Reduce space conditioning during non-working hours $685 - $385
8,364
kWh
- - $300
-
MMBtu
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,429 $2,713 $9,429
204,984
kWh
- - -
07 2.4221: Install compressor air intakes in coolest locations $1,048 $438 $1,048
22,776
kWh
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,181 - $1,181
25,667
kWh
- - -
TOTAL RECOMMENDED $69,498 $84,137 $31,798
691,241
kWh
$11,973
-
kW-mo/yr
$25,427 $300
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs