ITAC Assessment: OK0973
ITAC logo
ITAC Assessment: OK0973
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product RV air conditioning
NAICS 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area 156,000
ft2
Annual Production 450,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,221 3,078,553
kWh
Electricity Demand $137,062 6,722
kW-mo/yr
Electricity Fees $17,852 -
Natural Gas $37,647 4,913
MMBtu
TOTAL YEARLY COSTS $318,781
RECOMMENDED SAVINGS* $63,272 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,201 $28,109 $3,755
91,585
kWh
$3,446
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,650 $9,471 $2,919
71,197
kWh
$3,731
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $534 $2,111 $534
13,017
kWh
- - -
04 2.7232: Replace existing hvac unit with high efficiency model $4,431 $12,360 $1,494
36,451
kWh
$2,936
-
kW-mo/yr
- -
05 2.7224: Reduce space conditioning during non-working hours $2,172 - $280
6,836
kWh
- - $1,892
-
MMBtu
06 2.7211: Clean and maintain refrigerant condensers and towers $860 $769 $268
6,544
kWh
$591
-
kW-mo/yr
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,356 $19,135 $10,356
252,596
kWh
- - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,658 $1,650 $3,658
89,213
kWh
- - -
09 2.2437: Recover waste heat from equipment $8,097 $991 - - - $8,097
-
MMBtu
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,050 $510 $1,050
25,603
kWh
- - -
11 2.4221: Install compressor air intakes in coolest locations $1,046 $1,480 $1,046
25,521
kWh
- - -
12 2.3212: Optimize plant power factor $17,217 $17,024 - - $17,217 -
TOTAL RECOMMENDED $63,272 $93,610 $25,361
618,563
kWh
$10,705
-
kW-mo/yr
$17,217 $9,989
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs