ITAC Assessment: OK0970
ITAC logo
ITAC Assessment: OK0970
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Structural Steel
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $100
M
to 500
M
# of Employees 275
Plant Area 427,000
ft2
Annual Production 30,000
ton
Production Hrs. Annual 5,772
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $190,027 5,341,320
kWh
Electricity Demand $125,508 14,857
kW-mo/yr
Natural Gas $144,628 32,338
MMBtu
Waste Disposal Costs
Water Usage $15,046 3,140
Tgal
TOTAL YEARLY COSTS $475,209
RECOMMENDED SAVINGS* $103,786 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,359 $5,459 $5,359
148,857
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,255 $4,676 $2,255
62,650
kWh
- -
03 2.4221: Install compressor air intakes in coolest locations $1,299 $1,252 $1,299
36,086
kWh
- -
04 2.2437: Recover waste heat from equipment $2,913 $1,909 - - $2,913
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,763 $27,600 $16,763
465,627
kWh
- -
06 2.7241: Install outside air damper / economizer on hvac unit $4,582 $9,158 $4,582
127,280
kWh
- -
07 2.6218: Turn off equipment when not in use $11,037 $9,470 - - $11,037
-
MMBtu
08 2.7243: Improve air circulation with destratification fans / other methods $9,475 $7,530 $(-73.0)
(-2,020)
kWh
- $9,548
-
MMBtu
09 2.4322: Use or replace with energy efficient substitutes $30,101 $110,025 $30,101
836,142
kWh
- -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $20,002 $9,779 $13,987
388,515
kWh
$6,015
-
kW-mo/yr
-
TOTAL RECOMMENDED $103,786 $186,858 $74,273
2,063,137
kWh
$6,015
-
kW-mo/yr
$23,498
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs