| Assessment Year | 2017 |
|---|---|
| Principal Product | Structural Steel |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $100 M to 500M |
| # of Employees | 275 |
| Plant Area |
427,000
ft2
|
| Annual Production | 30,000
ton
|
| Production Hrs. Annual | 5,772
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $190,027 | 5,341,320 |
kWh
|
$0.036 | |
| Electricity Demand | $125,508 | 14,857 |
kW-mo/yr
|
$8.45 | |
| Natural Gas | $144,628 | 32,338 |
MMBtu
|
$4.47 | |
| Waste Disposal Costs | |||||
| Water Usage | $15,046 | 3,140 |
Tgal
|
$4.79 | |
| TOTAL YEARLY COSTS | $475,209 | ||||
| RECOMMENDED SAVINGS* | $103,786 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,359 | $5,459 |
$5,359
148,857
kWh
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,255 | $4,676 |
$2,255
62,650
kWh
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,299 | $1,252 |
$1,299
36,086
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $2,913 | $1,909 | - | - |
$2,913
-
MMBtu
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,763 | $27,600 |
$16,763
465,627
kWh
|
- | - | |
| 06 | 2.7241: Install outside air damper / economizer on hvac unit | $4,582 | $9,158 |
$4,582
127,280
kWh
|
- | - | |
| 07 | 2.6218: Turn off equipment when not in use | $11,037 | $9,470 | - | - |
$11,037
-
MMBtu
|
|
| 08 | 2.7243: Improve air circulation with destratification fans / other methods | $9,475 | $7,530 |
$(-73.0)
(-2,020)
kWh
|
- |
$9,548
-
MMBtu
|
|
| 09 | 2.4322: Use or replace with energy efficient substitutes | $30,101 | $110,025 |
$30,101
836,142
kWh
|
- | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,002 | $9,779 |
$13,987
388,515
kWh
|
$6,015
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $103,786 | $186,858 |
$74,273
2,063,137
kWh
|
$6,015
-
kW-mo/yr
|
$23,498
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs