ITAC Assessment: OK0968
ITAC logo
ITAC Assessment: OK0968
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Steel rod coil
NAICS 331110: Iron and Steel Mills and Ferroalloy Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $100
M
to 500
M
# of Employees 200
Plant Area 280,000
ft2
Annual Production 285,000
ton
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,420,634 171,432,800
kWh
Electricity Demand $2,046,092 607,149
kW-mo/yr
Natural Gas $1,405,796 459,651
MMBtu
Waste Disposal Costs
Water Usage $389,770 55,684
Tgal
TOTAL YEARLY COSTS $9,262,292
RECOMMENDED SAVINGS* $922,605 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $94,690

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,259 $3,000 $17,259
539,330
kWh
- -
02 2.6218: Turn off equipment when not in use $5,490 - $4,571
142,853
kWh
$919
-
kW-mo/yr
-
03 2.4221: Install compressor air intakes in coolest locations $3,554 $1,388 $3,554
111,049
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $55,717 $159,110 $48,693
1,521,664
kWh
$7,024
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $12,670 $90,081 $12,670
395,937
kWh
- -
06 2.5114: Use shaft type furnaces for preheating incoming material $670,334 $2,422,500 $547,200
17,100,000
kWh
$123,134
-
kW-mo/yr
-
07 2.2524: Avoid cooling of process streams or materials that must subsequently be heated $157,581 $3,000 - - $157,581
-
MMBtu
TOTAL RECOMMENDED $922,605 $2,679,079 $633,947
19,810,833
kWh
$131,077
-
kW-mo/yr
$157,581
-
MMBtu
TOTAL IMPLEMENTED $94,690 $253,579 $86,747
2,710,833
kWh
$7,943
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs