Assessment Year | 2017 |
---|---|
Principal Product | Steel rod coil |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
280,000
ft2
|
Annual Production | 285,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $5,420,634 | 171,432,800 |
kWh
|
$0.032 | |
Electricity Demand | $2,046,092 | 607,149 |
kW-mo/yr
|
$3.37 | |
Natural Gas | $1,405,796 | 459,651 |
MMBtu
|
$3.06 | |
Waste Disposal Costs | |||||
Water Usage | $389,770 | 55,684 |
Tgal
|
$7.00 | |
TOTAL YEARLY COSTS | $9,262,292 | ||||
RECOMMENDED SAVINGS* | $922,605 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $94,690 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,259 | $3,000 |
$17,259
539,330
kWh
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $5,490 | - |
$4,571
142,853
kWh
|
$919
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $3,554 | $1,388 |
$3,554
111,049
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $55,717 | $159,110 |
$48,693
1,521,664
kWh
|
$7,024
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,670 | $90,081 |
$12,670
395,937
kWh
|
- | - | |
06 | 2.5114: Use shaft type furnaces for preheating incoming material | $670,334 | $2,422,500 |
$547,200
17,100,000
kWh
|
$123,134
-
kW-mo/yr
|
- | |
07 | 2.2524: Avoid cooling of process streams or materials that must subsequently be heated | $157,581 | $3,000 | - | - |
$157,581
-
MMBtu
|
|
TOTAL RECOMMENDED | $922,605 | $2,679,079 |
$633,947
19,810,833
kWh
|
$131,077
-
kW-mo/yr
|
$157,581
-
MMBtu
|
||
TOTAL IMPLEMENTED | $94,690 | $253,579 |
$86,747
2,710,833
kWh
|
$7,943
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs