ITAC Assessment: OK0960
ITAC logo
ITAC Assessment: OK0960
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Chemical coated products
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 55
Plant Area 36,000
ft2
Annual Production 2,400,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,025 759,337
kWh
Electricity Demand $25,328 2,132
kW-mo/yr
Electricity Fees $223 -
Natural Gas $34,300 5,273
MMBtu
TOTAL YEARLY COSTS $122,876
RECOMMENDED SAVINGS* $11,764 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,728

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7135: Install occupancy sensors $287 $847 $263
3,167
kWh
$24
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,955 $5,880 $3,553
42,806
kWh
$1,402
-
kW-mo/yr
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $917 $600 - - $917
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,164 $3,055 $2,164
26,067
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $770 $150 $603
7,270
kWh
$166
-
kW-mo/yr
-
06 2.7243: Improve air circulation with destratification fans / other methods $2,672 $13,125 $186
2,235
kWh
$238
-
kW-mo/yr
$2,249
-
MMBtu
TOTAL RECOMMENDED $11,764 $23,657 $6,769
81,545
kWh
$1,830
-
kW-mo/yr
$3,166
-
MMBtu
TOTAL IMPLEMENTED $3,728 $14,122 $1,052
12,672
kWh
$428
-
kW-mo/yr
$2,249
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs