Assessment Year | 2016 |
---|---|
Principal Product | Food-safe printed matter |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
146,000
ft2
|
Annual Production | 200,000,000
units
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $137,265 | 3,036,859 |
kWh
|
$0.045 | |
Electricity Demand | $73,181 | 10,946 |
kW-mo/yr
|
$6.69 | |
Electricity Fees | $428 | - |
|
- | |
Natural Gas | $10,023 | 2,046 |
MMBtu
|
$4.90 | |
Waste Disposal Costs | |||||
Water Usage | $5,047 | 790 |
Tgal
|
$6.39 | |
TOTAL YEARLY COSTS | $225,945 | ||||
RECOMMENDED SAVINGS* | $29,798 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $13,063 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,635 | $15,400 | - | - | $6,635 | - | |
02 | 2.7241: Install outside air damper / economizer on hvac unit | $5,478 | $10,800 |
$5,478
121,736
kWh
|
- | - | - | |
03 | 2.7211: Clean and maintain refrigerant condensers and towers | $598 | $220 |
$445
9,886
kWh
|
$153
-
kW-mo/yr
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $2,925 | $572 |
$2,925
65,000
kWh
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $1,259 | $5,448 | - | - | - |
$1,259
-
MMBtu
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,112 | $1,100 |
$1,112
24,700
kWh
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $580 | $2,140 |
$465
10,340
kWh
|
$115
-
kW-mo/yr
|
- | - | |
08 | 2.7135: Install occupancy sensors | $8,841 | $4,680 |
$8,841
196,461
kWh
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,370 | $11,297 |
$2,370
52,660
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $29,798 | $51,657 |
$21,636
480,783
kWh
|
$268
-
kW-mo/yr
|
$6,635 |
$1,259
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,063 | $26,129 |
$12,795
284,322
kWh
|
$268
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs