ITAC Assessment: OK0935
ITAC logo
ITAC Assessment: OK0935
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Fabricated metal products
NAICS 332313: Plate Work Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 225,000
ft2
Annual Production 1,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,015 3,293,138
kWh
Natural Gas $99,523 14,072
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $84,588 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6232: Install set-back timers $7,525 $5,775 - $7,525
-
MMBtu
02 2.6125: Keep equipment clean $4,837 $750 - $4,837
-
MMBtu
03 2.2437: Recover waste heat from equipment $4,052 $1,913 - $4,052
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,207 $5,310 $1,207
16,310
kWh
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $765 $3,682 $765
10,331
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $19,536 $51,920 $19,536
264,000
kWh
-
07 2.4322: Use or replace with energy efficient substitutes $35,782 $17,000 $35,782
483,544
kWh
-
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,682 $1,170 $1,682
22,729
kWh
-
09 2.2514: Cover open tanks $8,035 $1,510 $8,035
108,579
kWh
-
10 2.1131: Repair faulty insulation in furnaces, boilers, etc $1,167 $1,000 - $1,167
-
MMBtu
TOTAL RECOMMENDED $84,588 $90,030 $67,007
905,493
kWh
$17,581
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs