Assessment Year | 2016 |
---|---|
Principal Product | Packaged meats |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $100 M to 500M |
# of Employees | 492 |
Plant Area |
300,000
ft2
|
Annual Production | 112,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $933,761 | 22,232,400 |
kWh
|
$0.042 |
Electricity Demand | $751,637 | 41,504 |
kW-mo/yr
|
$18.11 |
Natural Gas | $721,811 | 166,895 |
MMBtu
|
$4.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $426,172 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $77,686 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,999 | $48,276 |
$20,742
493,854
kWh
|
$12,257
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,290 | $20,770 |
$1,660
39,529
kWh
|
$2,630
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,485 | $7,280 |
$1,485
35,358
kWh
|
- | - | - | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $3,259 | - |
$1,494
35,565
kWh
|
$1,765
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2121: Increase amount of condensate returned | $24,062 | $20,162 | - | - | - | - |
$24,062
-
Tgal
|
- | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $2,272 | $3,404 | - | - | - |
$2,272
-
MMBtu
|
- | - | |
07 | 2.2135: Repair and eliminate steam leaks | $353 | $240 | - | - | - |
$353
-
MMBtu
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,193 | $83,117 |
$16,193
385,545
kWh
|
- | - | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,966 | $2,400 |
$8,966
213,475
kWh
|
- | - | - | - | - | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,618 | $10,720 |
$22,618
538,532
kWh
|
- | - | - | - | - | |
11 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $285,555 | $1,927,657 | - | - | $667,620 |
$(-382,065.1)
-
MMBtu
|
- | - | |
12 | 3.6125: Sell combustible waste | $24,120 | $480 | - | - | - | - | - | $24,120 | |
TOTAL RECOMMENDED | $426,172 | $2,124,506 |
$73,158
1,741,858
kWh
|
$16,652
-
kW-mo/yr
|
$667,620 |
$(-379,440.1)
-
MMBtu
|
$24,062
-
Tgal
|
$24,120 | ||
TOTAL IMPLEMENTED | $77,686 | $102,532 |
$34,347
817,781
kWh
|
$16,652
-
kW-mo/yr
|
- |
$2,625
-
MMBtu
|
$24,062
-
Tgal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs