| Assessment Year | 2016 |
|---|---|
| Principal Product | Magnetic separation equipment |
| NAICS | 331221: Rolled Steel Shape Manufacturing |
| SIC | 3264: Porcelain Electrical Supplies |
| Sales Range | $10 M to 50M |
| # of Employees | 136 |
| Plant Area |
65,000
ft2
|
| Annual Production | 20,000,000
lb
|
| Production Hrs. Annual | 4,940
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $45,064 | 1,121,760 |
kWh
|
$0.040 |
| Electricity Demand | $64,075 | 3,546 |
kW-mo/yr
|
$18.07 |
| Natural Gas | $9,914 | 1,448 |
MMBtu
|
$6.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,790 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $3,798 | $23,574 |
$1,991
46,307
kWh
|
$1,807
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,893 | $11,689 |
$1,429
33,236
kWh
|
$1,464
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,661 | $28,728 |
$4,782
111,209
kWh
|
$4,879
-
kW-mo/yr
|
- | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $2,634 | $8,294 |
$2,634
61,252
kWh
|
- | - | |
| 05 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,235 | $590 |
$349
8,126
kWh
|
$885
-
kW-mo/yr
|
- | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $1,555 | $1,498 | - | - |
$1,555
-
MMBtu
|
|
| 07 | 2.7231: Use radiant heater for spot heating | $2,973 | $11,940 | - | - |
$2,973
-
MMBtu
|
|
| 08 | 2.2437: Recover waste heat from equipment | $2,151 | $1,256 | - | - |
$2,151
-
MMBtu
|
|
| 09 | 2.4221: Install compressor air intakes in coolest locations | $143 | $182 |
$143
3,314
kWh
|
- | - | |
| TOTAL RECOMMENDED | $27,043 | $87,751 |
$11,328
263,444
kWh
|
$9,035
-
kW-mo/yr
|
$6,679
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,790 | $2,088 |
$349
8,126
kWh
|
$885
-
kW-mo/yr
|
$1,555
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs