ITAC Assessment: NV0115
ITAC logo
ITAC Assessment: NV0115
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Industrial Absorbent
NAICS
n/a
SIC 3295: Minerals and Earths, Ground or Otherwise Treated
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 80,000
ft2
Annual Production 52,440
ton
Production Hrs. Annual 6,240
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,734 2,214,537
kWh
Electricity Demand $48,921 5,653
kW-mo/yr
Electricity Fees $791 -
Fuel Oil #2 $27,728 16,878
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $439,969 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $75,705

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.3212: Optimize plant power factor $1,772 $2,333 - - $1,772 - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,392 $1,226 $2,441
58,324
kWh
$999
-
kW-mo/yr
$(-48.0) - -
03 2.4133: Use most efficient type of electric motors $4,937 $10,398 $3,541
84,701
kWh
$1,465
-
kW-mo/yr
$(-69.0) - -
04 4.446: Automate finishing process $68,996 $19,100 $(-184.0)
(-4,396)
kWh
$565
-
kW-mo/yr
$(-25.0) - $68,640
05 4.441: Install automatic packing equipment $358,805 $198,720 $(-655.0)
(-15,533)
kWh
$(-10.0)
-
kW-mo/yr
$7 - $359,463
06 3.5315: Lease / purchase baler; sell cardboard to recycler $2,067 - - - - $2,067
-
lb
-
TOTAL RECOMMENDED $439,969 $231,777 $5,143
123,096
kWh
$3,019
-
kW-mo/yr
$1,637 $2,067
-
lb
$428,103
TOTAL IMPLEMENTED $75,705 $31,831 $3,357
80,305
kWh
$2,030
-
kW-mo/yr
$1,678 - $68,640
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs