| Assessment Year | 2015 |
|---|---|
| Principal Product | Business forms |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2761: Manifold Business Forms |
| Sales Range | $5 M to 10M |
| # of Employees | 73 |
| Plant Area |
110,000
ft2
|
| Annual Production | 10,800
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $198,366 | 3,641,800 |
kWh
|
$0.054 |
| Electricity Demand | $60,620 | 8,514 |
kW-mo/yr
|
$7.12 |
| Natural Gas | $15,678 | 3,528 |
MMBtu
|
$4.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $113,123 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $92,878 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7241: Install outside air damper / economizer on hvac unit | $21,773 | $7,320 |
$21,773
403,200
kWh
|
- | - | - | |
| 02 | 2.6232: Install set-back timers | $2,950 | $972 |
$2,223
41,170
kWh
|
- | - |
$727
-
MMBtu
|
|
| 03 | 2.7211: Clean and maintain refrigerant condensers and towers | $149 | $132 |
$103
1,889
kWh
|
$46
-
kW-mo/yr
|
- | - | |
| 04 | 2.7496: Install partitions to reduce size of conditioned space | $9,143 | $18,884 |
$7,028
130,153
kWh
|
- | - |
$2,115
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $988 | $2,440 | - | - | - |
$988
-
MMBtu
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,832 | $38,110 |
$9,174
169,882
kWh
|
$1,658
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,758 | $25,753 |
$16,015
296,570
kWh
|
$2,743
-
kW-mo/yr
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,204 | $5,149 |
$1,204
22,304
kWh
|
- | - | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,212 | $863 |
$2,212
40,978
kWh
|
- | - | - | |
| 10 | 2.4131: Size electric motors for peak operating efficiency | $6,912 | $5,775 |
$6,912
128,013
kWh
|
- | - | - | |
| 11 | 2.8114: Change rate schedules or other changes in utility service | $35,000 | $70,000 | - | - | $35,000 | - | |
| 12 | 2.3212: Optimize plant power factor | $2,621 | $20,000 | - | - | $2,621 | - | |
| 13 | 2.6218: Turn off equipment when not in use | $581 | $468 |
$581
10,764
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $113,123 | $195,866 |
$67,225
1,244,923
kWh
|
$4,447
-
kW-mo/yr
|
$37,621 |
$3,830
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $92,878 | $148,299 |
$52,704
975,993
kWh
|
$4,447
-
kW-mo/yr
|
$35,000 |
$727
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs