Assessment Year | 2024 |
---|---|
Principal Product | 1. Piezes, solenoids, switches, 2. Thermoplastics ( contactors and starters) |
NAICS | 335313: Switchgear and Switchboard Apparatus Manufacturing |
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
236,000
ft2
|
Annual Production | 50,000,000
units
|
Production Hrs. Annual | 6,656
hrs
|
Location (State) | Puerto Rico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $832,093 | 3,907,609 |
kWh
|
$0.21 | |
Electricity Demand | $89,566 | 11,166 |
kW-mo/yr
|
$8.02 | |
Electricity Fees | $5,881 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $6,444 | 54 |
Tgal
|
$120.16 | |
TOTAL YEARLY COSTS | $933,984 | ||||
RECOMMENDED SAVINGS* | $86,098 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.3125: Use distillation, evaporation to remove contaminants | $43,981 | $80,000 | - | - |
$6,444
-
Tgal
|
$37,537 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,805 | $1,620 |
$12,841
60,285
kWh
|
$1,964
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,219 | $14,799 |
$13,313
62,504
kWh
|
$906
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $8,976 | $11,882 |
$8,405
39,458
kWh
|
$571
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $4,117 | $1,690 |
$4,117
19,329
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $86,098 | $109,991 |
$38,676
181,576
kWh
|
$3,441
-
kW-mo/yr
|
$6,444
-
Tgal
|
$37,537 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs