ITAC Assessment: OK0888
ITAC logo
ITAC Assessment: OK0888
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Thermal process
NAICS 332811: Metal Heat Treating
SIC 3398: Metal Heat Treating
Sales Range $10
M
to 50
M
# of Employees 57
Plant Area 27,100
ft2
Annual Production 5,000,000
ton
Production Hrs. Annual 8,736
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $100,640 1,748,407
kWh
Electricity Demand $43,397 4,710
kW-mo/yr
Natural Gas $227,139 38,851
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,414 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,551

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,503 $1,800 $5,503
95,542
kWh
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,709 - $2,222
38,577
kWh
$487
-
kW-mo/yr
- -
03 2.4221: Install compressor air intakes in coolest locations $709 $1,293 $709
12,304
kWh
- - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $13,683 $6,800 - - - $13,683
-
MMBtu
05 2.2511: Insulate bare equipment $843 $1,390 $238
4,132
kWh
- - $605
-
MMBtu
06 2.1135: Repair furnaces and oven doors so that they seal efficiently $6,388 $4,000 - - - $6,388
-
MMBtu
07 2.2437: Recover waste heat from equipment $52,633 $210,000 - - - $52,633
-
MMBtu
08 2.7231: Use radiant heater for spot heating $1,977 - - - - $1,977
-
MMBtu
09 2.3212: Optimize plant power factor $9,969 $6,825 - - $9,969 -
TOTAL RECOMMENDED $94,414 $232,108 $8,672
150,555
kWh
$487
-
kW-mo/yr
$9,969 $75,286
-
MMBtu
TOTAL IMPLEMENTED $27,551 $12,600 $5,503
95,542
kWh
- - $22,048
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs